DDU-GKY: Project Progress Report

Years: 2020-2024

Project Duration 3 Years
State Name PUNJAB
Kaushal Bharat Project ID 1000120
Sanction Order Date 05-08-2019
Sanction Order No. PSDM/2019/6056
Total Target 452
Minimum Placement Target(70%) 324
Trained 452
Assessed 421
Certified 399
Appointed 424
Monthly Continuity (min.3 months) 353
Placed 317

Years: 2024-2025

Project Duration 1 Year
State Name Punjab
Kaushal Bharat Project ID
Sanction Order Date
Sanction Order No.
Total Target
Minimum Placement Target(70%)
Trained
Assessed
Certified
Appointed
Monthly Continuity (min.3 months)
Placed